|
PROJECT AUTHORIZATION |
PACKET ID: PMT-1YJK |
CONTRACT ID |
EMARS PROGRAM CODE |
AUTHORIZATION NO: |
|
1407301D |
14073 |
1 |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID |
PROJECT ID NUMBER |
FEDERAL PROJECT NUMBER |
6 YR PLAN ITEM NUMBER |
6 YR PLAN ITEM PARENT NUMBER |
|
105 290 6 000-002 |
|
07-80102 |
7-.- |
PROJECT TYPE |
PROJECT LENGTH |
NUMBER OF BRIDGES |
SYSTEMS |
MINOR WIDENING |
1.1180 MI |
|
|
PROJECT PHASE
&
RESPONSIBILITY |
PLANNING |
DESIGN |
RIGHT OF WAY |
UTILITIES |
|
|
|
|
CONSTRUCTION |
TITLE DEEDED TO: |
MAINTENANCE |
OTHER |
|
|
|
|
FUNDING & TIME
ACCOUNTABILITY |
PARTICIPATING AGENCIES |
FEDERAL |
|
STATE |
KYTC |
LOCAL |
|
OTHER |
|
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER |
PHASE |
FUND |
PROGRAM |
FEDERAL FISCAL YEAR |
STATE FISCAL YEAR
|
FEDERAL APPR
CODE |
CURRENT FUNDING REQUEST |
7-80102 |
D |
1100 |
FD04 |
|
2023 |
|
$415,000.00 |
CURRENT FUNDING REQUEST TOTAL: $415,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE |
TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING |
$0.00 |
DESIGN |
$1,226,000.00 |
UTILITIES |
$0.00 |
R/W |
$0.00 |
CONSTRUCTION |
$0.00 |
NON-HIGHWAYS |
$0.00 |
|
Total: $1,226,000.00 |
THIS MODIFICATION PROVIDES $450,000 FD04 FUNDS TO COVER FINAL DESIGN ACTIVITIES ON THE PROJECT. |
|
Project Approval Recommended By:
James Ballinger 5/24/2023 |
Signed and Approved by:
Jim Gray 5/25/2023 |
ITEM NO. |
COUNTY |
DIST |
FACILITY NAME
|
ROUTE |
LENGTH |
07-80102.00 |
SCOTT
|
7 |
CONNECTOR RD |
KY 2906 |
1.1180 MI |
IMPROVE CAPACITY AND ACCESS ON KY 2906 FROM US 460 TO US 62 (2020CCN) |